May 05 2025

Data Collection to start this week

May 12 2025

Temporary device trial - Start date

Staff installed rubber curb bump-out along with stops sign on 93rd Street at Russell Avenue. This created a 4-way stop intersections.  This trail will last approximately 6 to 8 weeks and will be removed in July.  At that time the intersection will be restored to its original configuration with 2-way stop control on Russell Avenue.

July 14 2025

Temporary Device Trial - Removal

Staff removed the the curb bump outs and stop signs on W 93rd Street.  The intersection has been restored to its original configuration as of Monday July 14, 2025